A new order for a GE Vernova 7HA gas turbine placed today would likely see delivery in late 2028 at the earliest, with potential delays extending to 2029–2030 depending on production ramp-up and order prioritization. This equates to a lead time of approximately 3–4 years from order date, though some reports indicate quotes up to … Read more